n. For each of the test positions of inclination, the maximum mechanical imbalance during operation and the
speed shall be shown. The mechanical imbalance when mounted in its normal position (horizontal or vertical) shall
be shown. A qualitative statement addressing the adequacy of the lubrication and other issues, identified in the
inclined operation test requirement, shall be included (see 4.6.14).
o. The heat-run test data shall consist of the line voltage and current, watts, torque, and speed immediately
before shut-down, elapsed time at the test load, the cold resistance, the cold ambient temperature, the hot resistance,
the hot ambient temperature and the temperature rise. The temperature rise of each bearing, as measured on the
outer ring, shall also be shown (see 4.6.16).
p. The dielectric test shall consist of the test voltage and the elapsed time of application. The report shall also
indicate whether the motor withstood the proof voltage (see 4.6.17).
q. The electrical balance data shall consist of each line current as measured immediately before shut-down of
the heat run and the associated percent current balance (see 4.6.18).
r. The sealed insulation system electrical test data shall consist of the test water's conductivity and surface
tension and values of insulation resistance, corrected to 77 °F (25 °C), after 1 minute, 10 minutes, 1 hour, and 24
hours of submergence. The insulation resistance, dry, corrected to 77 °F (25 °C), shall also be shown. A qualitative
indication shall be included addressing the outcome of the surge test (see 4.6.19.2).
s. The efficiency test data shall consist of line current and volts, watts, speed, torque, and efficiency (see
t. The preload device test data shall consist of the uncompressed length of the preload device before and after
full compression. The nominal design value of compression and the force measured to achieve that compression
shall also be shown (see 4.6.21).
The inspection of packaging test data shall consist of a qualitative evaluation of the sample packages.
u.
D.2.3 Periodic inspection report. The report shall contain results of the periodic tests/inspections as specified
in table XVIII as follows:
a. The test/inspection data shall be as specified in D.2.2, above, with the exception that the data requirement
of D.2.2 (i) is not required.
D.2.4 Conformance inspection report. The report shall contain results of the periodic tests/inspections as
specified in table XIX as follows:
a. The test/inspection data shall be as specified above for D.2.2(a) through (d), D.2.2(f) through (h), D.2.2(j),
D.2.2 m), D.2.2(p), D.2.2(r) and D.2.2(t).
D.2.5 Shock test extension report. The report shall contain the following:
a.
The drawing of the motor from which shock test acceptance is being extended.
b.
The drawing of the motor to which shock test acceptance is being extended.
c. A copy of the shock test and motor post shock inspection associated with the motor from which shock test
acceptance is being extended.
d. If extension is requested based on a Type A shock test, adequate detail of both auxiliaries should be
included to allow the determination of their similarity.
D.2.6 Summary. The report shall include a summary that contains the following information:
a. A brief discussion of the significant test/inspection results, observations, conclusions, and
recommendations covered in greater detail elsewhere in the report.
b.
Proposed corrective actions and schedules for failures or problems encountered.
c.
Identification of deviations, departures, or limitations encountered, referenced to the contract requirements.
d.
Tables, graphs, illustrations, or charts as appropriate to simplify the summary data.